|
Products
Interlocking Pavers
Permeable Interlocking Pavers
Retaining Walls
Concrete Blocks
Cultured Stone
Natural Stone
Brick
Glass Block
Stepping Stones
Septic Systems
Types
Gravity/Pump Dosing Tanks
Distribution Boxes
Drop Boxes
Septic Tank Installation
Accessories
Pump Accessories
Drain Fields
User Manual
Photo Gallery
Technical Information |
I. Excavation
- A. Be sure of outside dimensions of tank
- 1. Must have a minimum of 12" of clear space all the way around tank.
- 2. Take into account the base material and inlet elevation for hole depth
- a. The incoming line must have a minimum of 1/4" per foot slope from facility to tank.
- b. Allow a minimum of 4"-6" bedding material in bottom of hole; allow for over excavation if there are unstable soils.
- c. Must know the distance from outside bottom of tank to the invert of the inlet.
- B. Place excavated material in an area that will not be in the way of the delivery truck.
- 1. Most tank delivery vehicles require to be within about 6' of the hole.
II. Check area leading into the excavation site before delivery
- A. Check for low hanging wires.
- B. Check for trees, buildings, etc., that may be in the way of the boom.
- C. Look for mud, soft spots, steep grades, or tight corners.
III. Setting the tank in the hole
- A. Take safety measures.
- Do not stand in hole while tank is being placed.
- Watch for water coming into the hole and walls sliding off in the hole.
- Stay away from edge of hole and watch the equipment operator.
- B. Be sure the tank is level.
- C. Check for proper alignment between inlet pipe and tank inlet.
IV. Backfill instructions for 3000 gallon 2-piece
- A. Follow same guidelines for excavation
- B. Set bottom half in prepared hole and make sure it is level
- C. Place kent seal aroundthe tank and set top half onto bottom half ensuring the inlet is in the correct position.
- D. Backfill should be of proper size and gradation.
- No stones over 4" in diameter.
- Thick sand or pea gravel should be used as backfill to provide uniform support for the tank walls.
- Make sure the backfill contains sufficient moisture for proper compaction
V. Water testing instructions for 1-piece tanks
- A. After proper placement and backfill ensure the inlet and outlet are sealed from any infiltration or exfiltration.
- B. Bring the water level to a point 2" above the point of riser connection to the top of the tank.
- To prevent uplift damage to the top of the tank, do not put more than 2" of water into the riser.
- C. Measure the water loss, if there is no water loss during the first 24 hours the test is complete.
- Some water absorption may occur within the first 24 hours, if so, refill the the tank and determine the exfiltration over the next 24 hours.
- The water level should not drop over 1" in the riser.
VI. Water testing for the 3000 gallon 2-piece tank
- A. Make sure the inlet and outlet are sealed off from infiltration and exfiltration
- B. Backfill to a point just below the mid rib seam
- C. Bring the water level just above the mid rib seam (no more than 2") and check the seam for any leaks.
- D. If there are no leaks finish backfilling the tank and bring the water level to a point no more than 2" into the riser.
- E. If there is no water loss in the first 24 hours the test is complete
- Some water absorption may occur, if so, refill tank and measure the water loss over the next 24 hours and determine the amount of exfiltration.
- The water level should not drop over 1" in the riser.
Table 1: Relationship between Number of Bedrooms,
Occupancies, and Flow
| Bedrooms |
Qp* gpd/DU |
Occupants** capita |
Qc gpcd |
Qa gpd/DU |
| 1 |
200 |
2 |
55 |
110 |
| 2 |
300 |
3 |
50 |
150 |
| 3 |
375 |
4 |
50 |
200 |
| 4 |
450 |
5 |
45 |
225 |
* Peak day bedroom flows
(Qp) are based on typical administrative
rules. ** Occupancy is based on typical usage
of two occupants for the first bedroom and one
occupant per additional bedroom.
Concrete Tanks
- a. Walls, bottom and top of
reinforced concrete tanks shall be designed across the
shortest dimension using one-way slab analysis.
Stresses in each face of monolithically constructed
tanks may be determined by analyzing the tank
cross-section as a continuous fixed frame.
- b. The walls and bottom slab
shall be poured monolithically; alternatively, water
stops may be provided.
- c. Reinforcing steel shall be
ASTM A-615 Grade 60, fy = 60,000 psi. Details and
placement shall be in
accordance with ACI 315 and ACI 318.
- d . Concrete shall be
ready-mix with cement conforming to ASTM CI50, Type
II. It shall have a cement content of not less than
six (6) sacks per cubic yard and maximum aggregate
size of 3/4 inch. Water/cement ratio shall be kept low
(0.35±), and concrete shall achieve a minimum
compressive strength of 4000 psi in 28 days. The
Contractor shall submit a concrete mix design to the
Engineer for review and approval. Three (3) concrete
sample cylinders shall be taken and tested for each
tank manufactured until the manufacturer and Engineer
are satisfied that the minimum compression strength is
being obtained. To ensure compliance, the manufacturer
shall then make and set three (3) sample cylinders for
a minimum of 20% of the remaining tanks at the
discretion of the Engineer. If the minimum compressive
strength is not being obtained, the manufacturer shall
be required to make and test sample cylinders for each
tank manufactured. Calcium chloride will not be
allowed in the mix design. The cost of testing
cylinders shall be the tank manufacturer's
responsibility. The tank manufacturer may supply a
Swiss hammer for compressive testing in the field in
lieu of sample cylinders.
- e. Tanks may be protected by
applying a heavy cement-base waterproof coating
(Thoroseal® or equal), on both inside and outside
surfaces, in compliance with Council of American
Building Officials (CABO) report #NRB-168; 6181,
however the tank should be watertight without the
addition of seal coatings.
- f. Form release used on tank
molds shall be Nox CreteTM or equal. Diesel or other
petroleum products are not acceptable.
- g. Tanks shall not be moved
from the manufacturing site to the job site until the
tank has cured for seven (7) days or has reached
two-thirds of the design strength.
- h. Tanks shall be manufactured
and furnished with access openings of the size and
configuration to accommodate individual packaged pump
systems. For 24-inch diameter access risers, the tank
manufacturer shall cast in place a flanged tank
adapter to facilitate the bonding of a 24inch diameter
access riser. The flanged tank adapter shall be made
of 1/4" thick ABS and shall have an outside diameter
of 27 inches and an inside diameter of 22-3/4 inches.
The flanged adapter shall be Orenco Systems©, Inc.
Model PRTA24 or engineer-approved equal. The adapter
must have an overall height of no less than 3 inches
to allow 1-1/2" exposed for sufficient bonding area
once the adapter is installed in the tank. For 21-inch
and 30-inch diameter access risers, either a grooved
tank adapter plate (Model RRFTA or RRFTA30) or a
flanged tank adapter (Model FRTA30) may be installed
in the tank. The adapter shall be manufactured of
fiberglass or ABS and shall accommodate either a
21-inch or 30-inch diameter access riser.
- i. The septic tank and the top
slab shall be sealed with a preformed flexible plastic
gasket. The flexible plastic gasket shall be equal to
the flexible butyl resin sealant congeal CS-102 or
CS202 as manufactured by Concrete Sealants, Inc. of
New Carlisle, Ohio, and shall conform to federal
specification SS-S-00210(2i0A) and AASHTO
M-198.
- j. In order to
demonstrate watertightness, tanks shall be tested
twice prior to acceptance. Inlets to the septic
tank will be watertight pipe seal Cast-A-Seal™
(Manufactured by Press-Seal Gasket Corporation) or
equal as approved by the Engineer. Each tank
shall be tested at the factory, prior to shipping, by
filling with water to the soffit and letting
stand. After 24 hours, the tank shall be
refilled to the soffit and the exfiltration rate shall
be determined by measuring the water loss during the
next two (2) hours. Any leakage shall be cause
for rejection. After installation is completed,
each tank shall be filled with water to the point two
inches into the access riser and retested as
previously described (the field test period may be
reduced to not less than two (2) hours).
Backfill of a depth equal to the water height in the
riser must be in place over the tank to prevent damage
due to hydrostatic uplift. No tank will be
accepted if there is any leakage over the two (2) hour
period.
|
|